Ciliwung PHB Retaining Wall has Been Repaired
access_time April 30 2020 09:53 PM remove_red_eye 2751
Reported by Mustaqim Amna | Translated by Maria Inggita
Reported by Mustaqim Amna | Translated by Maria Inggita
South Jakarta Water Resources (SDA) Sub-agency has completed repair of Ciliwung connecting (PHB) channel's retaining wall on Jalan Asem Baris Raya, Kebon Baru, Tebet.
We start the repair from February 24 until April 26
South Jakarta SDA's Maintenance Section Head, Junjung conveyed, this retaining wall has length 26 meters and height 15 meters. His side completed the repair within 3 months.
"We start the repair from February 24 until April 26. Previously, it was collapsed due to porous wall," he mentioned, Thursday (4/30).
Kawi-Kawi Channel's Retaining Wall in Johar Baru Being RepairedDuring the repair, he continued, his side deployed 1 excavator and 1 dump truck to transport the material, as well as 25 personnel and the other 5 personnel from Tebet SDA Unit.
"I hope this repair can be useful for residents near the location, especially to prevent flood and landslide," he closed.